Triton Knoll Offshore Wind Farm reaches halfway milestone

Triton Knoll has achieved another major project milestone having now installed 45 of the 90 turbines planned for the offshore array. The first of Triton Knoll’s 9.5 megawatts (MW) turbines was installed in January 2021 and the project remains on track to complete offshore construction by the end of the year. Turbine commissioning will continue … Read more

Triton Knoll Onshore Substation Virtual Tour now launched

The Triton Knoll Onshore Substation has a very important role to play in ensuring the power generated from the offshore wind farm can be transferred into the national grid and, ultimately, into our homes to power all of our electrical items. There are many different components within the onshore substation each playing a key role … Read more

Foundations and export cables installed as Triton Knoll drives towards first power in 2021

90 state-of-the-art foundations now in position 2 lengths of 50km export cable connect offshore and onshore electrical systems Offshore construction continues on-programme. Triton Knoll has taken another huge step towards first power generation in early 2021, completing the installation of all 90 turbine foundations and two 50 kilometre long export cables, this week. The successful … Read more

Triton Knoll Offshore Windfarm donates vital funds to Lincolnshire Charities

Seven charities from Lincolnshire have each received a £1,300 donation from the Siemens and Triton Knoll Offshore Windfarm project safety charity fund. Each of the local good causes were nominated by the site team working at the onshore substation site near Bicker, Boston, and chosen because of their proximity to the construction project. The donations … Read more

Construction of offshore wind farm base completes at Grimsby’s Royal Dock

View our gallery of images Construction of a new multi-million pound operations base for Triton Knoll is now complete after national contractor Tolent handed over the project this week. Once fully fitted out, the operations and maintenance facility will become the long term regional home for a team of skilled technicians and support staff, responsible … Read more

First offshore cable makes landfall as installation progresses

First 25km of offshore export cable now installed from Lincolnshire landfall Construction remains on track for first power export in 2021. DISCOVER MORE about our offshore export cables in our latest project film Triton Knoll offshore wind farm has marked a significant step in the construction of its state-of-the-art electrical system, ahead of anticipated first … Read more

Key offshore milestone ensures Triton Knoll remains on track for 2021 generation

Second Triton Knoll Offshore Substation Platform successfully installed Critical component of the transmission infrastructure in place A key stage in the construction of Triton Knoll’s offshore electrical infrastructure was completed today, with the installation of the second offshore substation platform. The installation of Offshore Substation Platform (OSP) East, the last of the project’s two OSPs, … Read more