innogy acquires Statkraft’s 50 per cent share in Triton Knoll offshore wind project

innogy becomes sole owner of Triton Knoll project with a planned installed capacity of 860 megawatts Future ownership structure to be reviewed further Final investment decision planned for mid-2018   innogy and Statkraft have completed an agreement under which innogy has acquired Statkraft’s 50 per cent share in the offshore wind project Triton Knoll.   With the acquisition … Read more

UK-based MPI Offshore to head up foundations installation at Triton Knoll

Teesside-firm is latest UK supplier and demonstrates project commitment to ‘local’ content MPI will install all 92 foundations and 2 offshore substations Triton Knoll has today confirmed UK-based MPI Offshore Ltd as preferred supplier for the transportation and installation of its offshore wind turbine foundations and offshore substations. The Stokesley (Teesside) based outfit is one … Read more

Triton Knoll welcomes UK based Siemens Transmission and Distribution Ltd as preferred substation supplier

Appointment aligns with Triton Knoll’s low cost approach, and is a clear sign of commitment to UK firms Powerhouse Siemens’ appointment expected to drive significant engagement of UK supply chain Manchester-based offshore grid connections specialists will design electrical system, including supply and install of onshore and offshore substation   Triton Knoll Offshore Wind Farm has … Read more

Technology advances enable Triton Knoll to remove Intermediate Electrical Compound from final design

Triton Knoll News

·      Use of latest power flow management techniques will further minimise costs at wind farm ·      Removal of the Intermediate Electrical Compound is welcomed by Orby Parish Council The team behind the Triton Knoll Offshore Wind Farm have confirmed that they have been able to remove the Intermediate Electrical Compound (IEC) from their … Read more

Archaeological Trial Trenching underway

Triton Knoll started its Archaeological Trial Trenching campaign on Monday, July 31, 2017. If you would like to know more about these investigations, please see our Q&A document which should answer most queries. If you have any further questions or issues you’d like to raise, or would like to know more, please contact us either … Read more

Future proofing the workforce by supporting Humber UTC

Triton Knoll has been helping to ‘future proof’ the local workforce, by helping to foster an interest in Science, Technology, Engineering and Maths education through an open day at Scunthorpe engineering college Humber University Technical College (UTC). Project staff were recently on-hand to talk to new students considering a career in engineering, renewables and offshore … Read more

Walkover surveys commence at Triton Knoll

Triton Knoll News

Triton Knoll is continuing to progress low impact survey works along the length of its proposed cable route, which runs from the landfall at Anderby Creek, through to Bicker Fen where the power generated by the offshore wind farm will ultimately connect into the national grid network. Due to start on 24 October, up to … Read more